Belmont Area, Ayr

We’re carrying out safety-critical work to upgrade our gas network in the Belmont area of Ayr.

In agreement with South Ayrshire Council our project will start on Monday 14 June 2021 and last approximately 46 weeks.

By upgrading our gas network in the Belmont area, we’ll continue to keep Ayr homes and businesses safe and warm long into the future.
 

Phase one – approx. 10 weeks
 

The first phase of this project will begin on Monday 14 June; we’ll install temporary two-way traffic lights on Dalmellington Road, between Forest Way and Belmont Road, for around two weeks. We’ll also be working in Ewenfield Road, Ewenfield Park and Ewenfield Place.

From Saturday 26 June, we’ll begin working in Belmont Road. To ensure everyone’s safety, we’ll be closing Belmont Road at both ends (at its junctions with Maybole Road and Dalmellington Road). We’ll also need to install temporary three-way traffic lights at these junctions.

While Belmont Road is closed, our teams will progress along it and then into Nursery Road and Peggieshill Road. They will also be working in Maybole Road, between its junction with Belmont Road and the Kwik Fit garage, and in Fenwickland Drive between Belmont Road and Peggieshill Road.

On Saturday 10 July, we’ll reopen Belmont Road at the Dalmellington Road end for local access. We’ll also remove the temporary three-way traffic lights at this end. However, the road closure and temporary lights at Belmont Road’s junction with Maybole Road, will remain in place until around Saturday 21 August.

You can see this first phase highlighted in yellow on the map below. Details for work in the streets highlighted in blue are yet to be finalised.

All phases and durations may be subject to change as the project develops, but we’ll keep you updated with our progress right here.