We’re upgrading our gas network in the Frimley Road area of Camberley. This essential work needs to go ahead now to ensure your local community continues to receive a safe and reliable gas supply.

In agreement with Surrey County Council, our project will start on Monday 16 May and last approximately 16 weeks. For everyone’s safety, it will be necessary to use a variety of traffic management measures including temporary traffic signals and road closures.

 

Phase 1 – Frimley Road

From Monday 16 May to Thursday 30 June, we'll be working on Frimley Road between its junctions with Edward Avenue and Harcourt Road. For everyone's safety, we'll need to install temporary three-way traffic lights around our work area.

 

Phase 2 – Gordon Road

From Monday 13 June to Friday 5 August, we'll be working in sections along Gordon Road. We'll need to close Gordon Road in sections to keep everyone safe as we progress along the road.

Section 1: from outside 128 Gordon Road to the junction with Garfield Road

Section 2: from the junction with Garfield Road to the junction with Park Street

Access to Garfield Road will be maintained, with the direction of access will changing dependent on our work section - local signage will keep road users advised.

 

Phase 3 – Park Street

From Wednesday 20 July to Friday 5 August, we'll be working on Park Street between its junctions with Middle Gordon Road and Gordon Road. For everyone's safety, a temporary road closure will be in place with a signed diversion route for road users.

There will be no through vehicle access past our closure, with access maintained for pedestrians and cyclists.

Vehicle access arrangements will be in place for properties within the closure and our team will keep those impacted informed of local arrangements.

 

Phase 4 – Frimley Road

Once Park Street has reopened, we'll need to return to Frimley Road to complete our project - the earliest date for this will be Monday 1 August and we aim to complete our work by Wednesday 31 August.

Frimley Road will be temporarily closed between its junction with Alexandra Avenue to just north of Woodlands Road. Vale Road will also be temporarily closed at its junction with Frimley Road. Access to Vale Road will be via short signed diversion.

 

We understand that people can get frustrated by roadworks. We would like to thank the local community for their patience and understanding while we carry out this essential work.