Elgin area

We'll begin to upgrade our gas network in various areas of Elgin on Tuesday 6 April. 

Our safety-critical project to upgrade the gas network in Elgin needs to go ahead now, rather than wait until the covid-19 pandemic passes, to ensure your local community continues to receive a safe and reliable gas supply for many years to come. We’re working closely with Scottish Government to make sure we carry out our project in line with all current coronavirus safety guidance.

To minimise disruption as much as possible, we'll carry out our work in five phases. This page will be updated as we reach each stage of our project. 

Phase three - 6 September

For the first six weeks of phase two we'll be working in Blantyre Place. To allow our engineers to work safely, a one-way system will be in place for motorists. 

At the same time, we'll be working in Mitchell Crescent and Brodie Drive for approximately eight weeks. After this work is completed, our engineers will move into phase four of our project. 

We'll keep you updated here.