Troon, South Beach

Update 18 May

Work is underway and is progressing well meaning we are able to revise our schedule of works as follows:

  • Phase 1 – We anticipate this phase will be complete by 29 May.
  • Phase 2 – We’ll begin working from the junction of Yorke Road along South Beach to the junction with Craigend Road on 23 May for approximately four weeks. Then around 13 June for five weeks we’ll be working on Craigend Road from the junction of South Beach to no. 9 Craigend Road.
  • Phase 3 – We’ll begin this phase around 13 June for four weeks, working in Crosbie Court and Warrix Gardens.

 

 

We’re investing £454,000 to upgrade our gas network in the South Beach area of Troon.

This essential work needs to go ahead now to ensure your local community continues to receive a safe and reliable gas supply.

In agreement with South Ayrshire Council and Ayrshire Roads Alliance, our project will start on Monday 9 May and last approximately 24 weeks. Our work will mainly be carried out on footpaths or using give and take traffic management however, temporary traffic lights may be required at the junction of Yorke Road and South Beach during our project’s second phase.

Media library image
A map showing the phases of our project

Phase one – approximately 9 weeks

On Monday 9 May we’ll begin work in South Beach, at its junction with Craigend Road. We’ll be moving north up to outside number 86 South Beach. We’ll then be working at the rear of number 86, continuing north at the rear of properties on South Beach, until we reach St Meddens Street.
 

Phase two – approximately 11 weeks

From Monday 4 July, we’ll start working from South Beach’s junction with Yorke Road. We may need temporary three-way traffic lights for everyone’s safety while we’re working at this junction. We’ll then progress south towards Craigend Road, and then move east along Craigend Road up to number 9. During this phase, we’ll need to carry out some work in Crosbie Court.
 

Phase three – approximately 4 weeks

From Monday 29 August, we’ll be working Crosbie Court and Warrix Gardens.

 

Our work will mainly be carried out on footpaths or using give and take traffic management however, temporary traffic lights may be required at the junction of Yorke Road and South Beach during our project’s second phase. Bus stop and cycle lane closures will also be required.

We are also aware of a planned event – the Glasgow Taxi Drivers’ Outing to Troon on 15 June and we will be ceasing operational work in advance of this day and ensuring that the site is both safe and tidy.