Applying online is the quickest and easiest way to get a quote for a new gas connection, but there are a few things to check before you start.
Are we your gas network operator?
Enter your postcode
Check our current costs and leadtimes
Check our current costs and leadtimes
Selected location: Scotland
ResetNew connection cost
Cost | |
---|---|
If SGN dig the trenches | £893 +VAT |
If you dig the trenches | £731 +VAT |
Current lead times
6-8 weeks from accepting your quote. Once you have accepted your quote and paid for the work, an Account Manager will contact you to discuss suitable dates.
Check our current costs and leadtimes
Selected location: Southern England (inside M25)
ResetNew connection cost
Cost | |
---|---|
If SGN dig the trenches | £1259 +VAT |
If you dig the trenches | £1010 +VAT |
Current lead times
6-8 weeks from accepting your quote. Once you have accepted your quote and paid for the work, an Account Manager will contact you to discuss suitable dates.
Check our current costs and leadtimes
Selected location: Southern England (outside M25)
ResetNew connection cost
Cost | |
---|---|
If SGN dig the trenches | £1141 +VAT |
If you dig the trenches | £913 +VAT |
Current lead times
10-12 weeks from accepting your quote. Once you have accepted your quote and paid for the work, an Account Manager will contact you to discuss suitable dates.
Before you apply
Site plan
If your property is a new build or conversion, we need a site plan to work out where the pipe needs to go. You can upload one during the application process.
Permission
The land that we need to access must be owned by you, or you’ll need written permission from the landowner for the work.
If you need planning permission, or a local authority permit, please make sure these are in place.
Here to help
Your quote
Apply online to get a quote for a new gas connection to any single domestic property.
If your work is a standard connection, we’ll email your quote immediately.
If you don’t receive a quote, it could be because the information you provided doesn’t allow us to create an instant quote. Our specialist team will review your application and send a quote as quickly as possible. They’ll let you know if we need anything else.
This could apply if:
- You need more than 23 meters of pipe
- You live in a flat on the second floor or above
- You have a heated swimming pool
- You have 5 bedrooms or more
Multiple properties
If your application is for business premises, multiple properties or one property which needs multiple connections, please use our commercial application form.
No. You’ll need to contact a gas supplier to arrange for a meter to be fitted. We’ll provide you with a meter point reference number and we recommend you contact your supplier as soon as we have a date for the work.
We’ll do all we can to make the job easy for you and your neighbours. We may need to close the pavement or road outside your house, but we’ll discuss that with you before we start our work.
No. Anything that we dig up to install your new gas connection will be tidied up within 5 working days of the job by our specialist reinstatement team. That includes holes in the road or pavement.
Most jobs can be completed within one day. If yours has special requirements and could take longer, we’ll let you know well in advance and discuss it with you.
We’ll discuss possible dates with you and do whatever we can to plan the job for a date that suits you.
What happens next?
Accept & pay
If you apply online and receive a standard quote, you can accept your quote and pay online by debit card, credit card or PayPal.
Planning your work
We’ll check your quote and contact you if there are any problems. Otherwise, we’ll be in touch within 7 working days to arrange your connection.
Get connected
How to prepare for our work and what to expect while we are installing your new gas connection.