We’re working on a 30-year programme to upgrade our gas network. We’re replacing old metal pipes with new plastic pipe to ensure homes and businesses in the south of England and across Scotland continue to receive a safe and reliable gas supply for years to come.
Here’s some of our major upgrade projects. You can find details of all our other upgrade projects, as well as emergency work, on the Roadworks in your area page.
Start date: 18 Nov 2025
Duration: Five weeks
Start: 3 Nov 25
Duration: Three months
Avenue Road, Bexley
Start date: 20 October
Completion date: 15 December
Start: Mon 5 Jan
Duration: Three months
Start: 5 Jan 2026
Duration: 18 weeks
Start date: 27 January 2025
Duration: 11 months
Start: 2 February 2026
Duration: Five weeks
Starts: 12 November
Duration: 12 weeks
Start date: 11 August 2025
End: March 2026
Russell Hill Road, Croydon
Start date: Monday 10 November
Duration: approximately 14 weeks
Start: Mon 5 Jan
Duration: Five weeks
Start date: 26 January 2026
Duration: six weeks
Starts: 26 January
Duration: 5 weeks
Start date: Monday 26 January
Duration: 5 weeks
Curlew Crescent, Greenock
Start date: 28 August
Duration: 12 weeks
Start: 3 February 2026
Duration: Three weeks
Start date:8 September 2025
Duration: 7 months
Start: 5 January 2026
Duration: Three weeks
Start: Mon 1 Sep
Duration: Eight months
Inverness, A96 Raigmore Interchange
Start: February 2026
Duration: 15 weeks
Kidbrooke Gardens, Greenwich, London
Start: 21 July 2025
End date: 2 November
Stevenston Road, Kilwinning
Start date: 21 August
Duration: Three weeks
We’ll be working in the Rushey Green area of Lewisham in the New Year to upgrade the gas network.
We’ll start work on Monday, 05 January, and continue until the end of March.
Start: 5 January 2026
Duration: 16 weeks
Start: 17 June 2024
Duration: 5 months
Upton Road, Poole
Start date: Monday 6 October 2025
End date: Friday 20 February 2026
Stride Avenue and surrounding roads, Portsmouth
Start: June 2025
End: August 2026
Selcroft Road, Purley
Start date: Monday 3 November
Completion: February 2026
Albion Road, Sandhurst
Start date: 15 September
Completion date: March 2026
Start date:8 September 2025
Duration: 7 months
Start: Mon 26 Jan
Duration: Three months
Start: Autumn 2024
Duration: 18 months
Start: 5 Jan 26
Duration: Ten weeks
Start: 27 October 2025
Duration: 28 weeks
Victoria Road, Worthing
Start date: 27 October
Completion date: April 2026
Start: Mon 5 Jan
Duration: Eight months
Earlsfield Road, Wandsworth
Start date: 29 September
Duration: approximately 8 weeks
Earlton Road, Wandsworth
Start date: 29 September
Duration: approximately 10 weeks
Valley Road, Wareham
Start date: 19 August
Duration: 29 weeks
Start: 6 November 2025
Duration: Up to six weeks