Birnam to Logierait project

AUG
30

Project update: 30 August

Phase 3 - B898 - pipelaying now complete

Our work is continuing to progress well and all of our the pipelaying work in the B898 is now completed, shown in the map below.

Reaching this stage means we continue to be ahead of schedule.

Now the new pipe is fully laid in the road, work continues for safety monitoring, engineering tests and general commissioning work. We estimate this final element of work will be finished by early November 2024.

We require a one-day road closure to complete a road crossing during the week commencing 23 September and will give as much advance notice as possible.

We will continue to keep you informed with the progress we are making on the project with regular updates and an accompanying map.

There's more information here in our project leaflet.

Media library image
current project area map

Project background

One of our gas pipes runs close to the River Tay, and due to some erosion on the river bank we need to move and upgrade this section of our network.

Our gas network in the area remains safe and there's no immediate risk, but we want to carry out our construction work now to ensure a safe and reliable gas supply.

Our new pipeline will run between Birnam and Logierait and the project is being carried out by our contractors Advance Group Limited and Morrison Energy Services.

Media library image
Birnam to Logierait phases two and three project map showing work areas and diversion routes

phases two and three project map

There's more information in our bespoke project booklet.

Keeping you informed

We have held multiple drop-in sessions to share details about our plans, answer questions and receive feedback. If you were unable to attend these sessions, you can download the information boards.

You can also keep updated with our plans, or advise us on any special events we should be aware of, by signing up to our project email distribution list.

We're updating this dedicated web page as our project progresses, writing to affected residents to keep them informed, and publishing project milestones in The Bridge community newsletter.

If you have any questions about this project, you can get in touch with us at birnamtologierait@sgn.co.uk.