We’re upgrading our gas network in Main Road, Condorrat. This essential work needs to go ahead now to ensure your local community continues to receive a safe and reliable gas supply for many years to come.
Working to keep you safe and warm
What we're doing
We're replacing our old metal pipes in Main Road. This is part of our 30-year programme of work to replace our old mains, reaching the end of their useful lives, with new, reliable plastic pipe.
When we're working
In agreement with North Lanarkshire Council, our project will start on Monday 1 April and last approximately eight months.
We’ll be working in Main Road, Condorrat, in sections. We’ll begin from near its junction with Medrox Gardens, progressing north east up to its junction with Maree Drive, where Main Road becomes Condorrat Ring Road.
The above map shows each section including whether we’ll need implement a full road closure or use temporary traffic lights. If we need a road closure, signed local diversion routes will be clearly sign posted.
The following details the dates for each of the sections outlined in the map:
- Section one: 1 April to 12 April
- Section two: 15 April to 24 May
- Section three: 20 May to 31 May
- Section four: 3 June to 28 June
- Section five: 24 June to 5 July
- Section six: 8 July to 19 July
- Section seven: 15 July to 26 July
- Section eight: 29 July to 16 August
- Section nine: 12 August to 30 August
- Section 10: 26 August to 6 September
- Section 11: 9 September to 27 September
- Section 12: 23 September to 18 October
- Section 13: 21 October to 8 November
- Section 14: 4 November to 22 November
As a consequence of the full road closures affecting Condorrat Main Road, bus services will be diverted to operate via Condorrat Ring Road, Maree Drive and the M80. For further information, click on the button below or contact