Finchampstead, Nine Mile Ride

Following multiple leaks in our gas network, we will be replacing the old metal gas pipes with new plastic pipes in Nine Mile Ride and at the junction of Old Wokingham Road and Nine Mile Ride. This work needs to be started urgently to enable us to continue to provide a safe and reliable gas supply and to minimise the risk of further leaks in the area.

Our contractors, I&G Contractors, will be completing this work on our behalf and will start work on Monday 4 December.

The work will be carried out in two phases:

 

Update - 2 January 2024

Phase one has been completed and phase two will start on Wednesday 3 January as planned.

 

Phase one

We'll be working from Monday 4 December until Sunday 17 December to replace the pipe in Old Wokingham Road at its junction with Nine Mile Ride (at the roundabout).

To complete this work safely we will need to:

  • Close the entrance and exit to Old Wokingham Road from Nine Mile Ride at the roundabout.
  • Install temporary traffic lights approaching the Nine Mile Ride/Old Wokingham Road roundabout to allow traffic to flow past our working area in Old Wokingham Road.
  • Temporarily suspend the bus stop within our work area.

Access for residents and businesses will be maintained and a signed diversion route will be in place.

We will reopen the road for the festive period from Friday 15 December until Tuesday 2 January 2024. Our work will start again from Wednesday 3 January 2024. There will be no carriageway incursion during this period.

 

Phase two

We will return to Nine Mile Ride on Wednesday 3 January 2024 to replace the gas pipe network in the carriageway between Old Wokingham Road and Palmer Close.

To ensure the safety of everyone around our worksite, we will be closing Nine Mile Ride in phases around our work area where the pipe is being replaced. The phases are planned as follows

  • Nine Mile Ride Roundabout to The Nine Mile Ride/Lupin Ride footpath
  • The Nine Mile Ride/Lupin Ride footpath to Palmer Close (including Palmer Close)

This work is expected to last until late May 2024.

Thank you to the local community for their patience while we complete our work and sorry for any inconvenience this may cause.

 

Drop in session

We'll be hosting an online meeting for the local community to discuss this project and answer any questions they may have.

The meeting will take place on Microsoft Teams on Thursday 30 November at 4pm (a change from the original date and time).

You can join the meeting here or you can call 0203 321 5202 and quote meeting ID 301343195.