Hastings, B2093 The Ridge

NOV
13

Update - Friday 13 November

We've now started the second phase of our gas network upgrade project in the area, between Stonestile Lane and Elphinstone Road. Thanks to the great progress made so far, we're currently around four weeks ahead of schedule.

Four-way temporary traffic lights at the junctions of Stonestile Lane and Chowns Hill are now in operation for everyone's safety. These lights include a pedestrian crossing phase to maintain safe access for those on foot.

To help minimise disruption, we have operatives managing the lights between 7am and 7pm. These operatives are monitoring traffic conditions and adjusting signal timings where possible.

If work continues to progress as planned, we're hopeful the four-way lights can be reduced to three-way by Friday 20 November, and then two-way by Friday 27 November.

Our work will be temporarily suspended from the end of the day on Friday 11 December for the Christmas period. All traffic management will be removed while work is paused. Our engineers will resume work the week beginning Monday 4 January.

We'd like to thank the Hastings community for their ongoing patience and cooperation while we carry out this essential work to upgrade our gas network and maintain a safe and reliable gas supply for local homes and businesses.

We're carrying out essential gas network upgrades in the B2093 area of Hastings. This work will ensure a continued safe and reliable supply of gas is delivered to nearby homes and businesses.

Working to keep you safe and warm

What we're doing

We'll be replacing our old metal pipes - laid around a century ago - in the B2093 area. This is part of our 30-year programme of work to replace our old mains, reaching the end of their useful lives, with new, reliable plastic pipe.

When we're working

Our work will start on Tuesday 22 September and be carried out in six phases to help minimise disruption. This project is expected to finish in mid-August 2028.

Temporary traffic lights on the B2093

To ensure everyone's safety while this work is carried out, temporary traffic lights will be installed around our work area as we progress.

These lights will be manually operated to ensure traffic continues to flow on this sensitive route. However, we'd recommend motorists allow extra time for journeys while the lights are in operation.

Our phases of work along B2093 The Ridge

Starting on Tue 22 Sep 2026

  • We'll be working between its junctions with Grange Road and Stonestile Lane
  • Our engineers will be replacing 600m and upgrading 30 services to adjoining properties
  • We're hopeful of finishing this phase by Fri 11 Dec 2026

Starting on Mon 4 Jan 2027

  • We'll be working between its junctions with Stonestile Lane and Elphinstone Road
  • Our engineers will be replacing 650m and upgrading seven services to adjoining properties
  • We're hopeful of finishing this phase by Mon 5 Apr 2027

Starting on Mon 28 Jun 2027

  • We'll be working between its junctions with Elphinstone Road and Norcross Close
  • Our engineers will be replacing 700m and upgrading 11 services to adjoining properties
  • We're hopeful of finishing this phase by Mon 13 Sep 2027

Starting on Sat 16 Oct 2027

  • We'll be working between its junctions with Grange Road and Stonestile Lane
  • Our engineers will be replacing 28m of our old metal main
  • We're hopeful of finishing this phase by Sun 31 Oct 2027

Starting on Mon 3 Jan 2028

  • We'll be working from opposite Maitland Close, past Hillside Road and Beany's Lane, to just short of the Conquest Hospital roundabout
  • Our engineers will be replacing 425m and upgrading 38 services to adjoining properties
  • We're hopeful of finishing this phase by Mon 28 Feb 2028

Starting on Mon 26 Jun 2028

  • We'll be working between Norcross Close just past the junction with Pine Avenue
  • Our engineers will be replacing 450m of our old metal gas main
  • We're hopeful of finishing this phase by Mon 21 Aug 2028

Media library image
A map showing the work phases for upgrades along B2093

Small businesses affected by planned streetworks

For business customers only, compensation can be claimed for loss of gross profit and not loss of takings, subject to your claim meeting the criteria in The Gas (Street Works) (Compensation of Small Business) Regulations 1996. To find out if you qualify, please complete our online business compensation form.

Before you apply for business compensation, to save you time and ensure you are eligible to apply, please ensure the following:

  • SGN engineering work must have lasted continuously for at least 28 days.
  • Annual turnover in aggregate must be less than £1 million at 1996 prices (£1.918 million for 2020/21). The annual turnover figure includes not only the business affected by our work but also the turnover of any associated businesses of the same type, operating from different premises.
  • The claimed loss of gross profit must be at least 2.5% of annual turnover (the minimum claim is £500).
  • The initial written indication of your intention to claim must be submitted within three months of the completion of SGN engineering works.
  • Supporting evidence including financial statements and documentation must be submitted within six months of completion of engineering works.
  • A statement of the calculated loss of profit that you wish to claim.

We're arranging a virtual drop-in session for businesses wanting to attend. Interested businesses can register their interest by completing this form.

We'll be updating this page with our progress, but you can also receive email updates on our project by completing this form.

We recognise roadworks can be frustrating. However, the new plastic pipe has a lifespan of 80 years. This means that once our essential upgrade project is complete, Hastings residents and businesses will be able to enjoy the benefits of a safe and reliable gas supply for many years to come.