Scotstoun, Glasgow

We're carrying out essential upgrades to our gas network in Scotstoun, Glasgow. This work has been planned in close consultation with Glasgow City Council and will ensure a continued safe and reliable gas supply to nearby homes and businesses.

Working to keep you safe and warm

What we're doing

Our engineering team is replacing old metallic mains with modern plastic pipe which has a lifespan of 80 years.

When and where are we working

Our project started in 31 March 2025 and the first phase will last for approximately six weeks. Our work will take place in the streets south of Scotstoun Stadium.

We’ll be working in the streets marked out in the map below. Our work will be carried out in phases as highlighted. During the course of phase one of our work the following roads will need to be closed during these dates:

  • Verona Avenue will be closed from 07/04/25 until 20/04/25 
  • Dunglass Avenue will be closed from 21/04/25 until 04/05/25
  • Ormiston Avenue will be closed from 05/05/25 until 18 /05/25
  • Earlbank Avenue will be closed from 19/05/25 until 15/06/25

We'll provide more details on the subsequent phases on this page when it becomes available,